Setup Crew Variable

Chad B. shared this question 4 months ago
Answered

I see that we now have a variable for rental_setupcrew, which is awesome.


Can we also get one that is for the lead? I imagine this would be done by grabbing whatever the largest item on the lead would require for the setup crew OR whatever is manually entered.

Comments (2)

photo
1

I have your request in with devs and you'll be notified when we have an update.

photo
1

I'm not sure I understand your request, but here's me trying.

*setupduration* is used to get the planned setup time for the lead. Technically since we know the setup man hours for each item and we know how many people you are sending for setup, we could calculate it. We haven't tried that yet, but what we would do is recommend a different setup duration since you have told us how many people you are sending. This would likely be a warning as well as changing the recommended time shown on the timeline.

photo
1

Actually, it's not the duration at all. On each inventory item, I can now set the number of crew it takes to set up each piece *rental_setupcrew*. On the lead where the lead weight, setup crew, operating crew, electrical, and volunteers is calculated is a field that I assume sums up the number needed for the lead. I'm not 100% sure how that field works yet since I'm still adding in the setup crew for items BUT what I am asking for is a variable to display the Leads Total setup crew needed that is calculated there in that field. Image below


cf7de968c40ec939ee4b1fae8b8bbb94

photo
1

Got it. We will work on it.